Risk management according to IPMA: how to describe, weigh, and manage risks

Everyone on your project team sees something coming. The schedule is tight, the supplier is slow to respond, and that one specialist might want to leave. Yet, it often remains just a gut feeling. IPMA provides a clear approach to precisely describe these concerns and weigh them carefully. With 8 measures, you can then make targeted choices about what to do about them.

Briefly
Risk management according to IPMA means continuously recognizing, analyzing, assessing, and controlling the risks and opportunities in your project. You communicate about this with the people involved. You describe each risk in one sentence, including cause, event, and consequence. Then you weigh it based on probability and impact and choose from 8 risk mitigation measures.

Why is a concern not yet a risk?

A concern is a vague feeling that something might go wrong. Compare it to a gut feeling; it is something you want to acknowledge at the start of your project. However, you do not yet know exactly what is causing it, what will happen, or what it will cost your project. A risk, on the other hand, is much more concrete. IPMA defines a risk as an event that could occur in the future, due to a specific cause, with negative consequences for your project.

The difference, therefore, lies in three things: the cause, the event, and the consequence. A concern mentions at most one. A risk mentions all three. And only when you know those three can you estimate how likely it is and how great the damage could be.

An example. During the kick-off, someone asks if there are any risks, and just like that, within 5 minutes the whiteboard is full. Planning tight. Budget tense. IT? Everyone nods in agreement. After that, little happens, because what do you do with “IT?” You cannot weigh or address a loose slogan. For that, you need a sharper definition. IPMA Compact contains a sentence structure that does exactly that.

How do you record a risk?

You describe a risk in three parts: because (cause), the risk arises that (event), and with the result that (impact) . The book IPMA Compact provides an example from production. During the holiday period, there are too few skilled employees. As a result, the risk arises that the machines are not used properly, resulting in rejected products.

Do you see what is happening? Suddenly you know where you can intervene: at the cause, at the event, or at the consequence. You will encounter those three points of intervention again later regarding the measures.

Is every uncertainty a risk?

No. According to IPMA, something is only a risk if you do not know whether an event will occur. If you do know, then you have something else going on. There are two situations that are often confused with risks.

  1. An uncertain estimate
    Are you unsure whether testing will take 10 or 15 days? That might feel like a risk, but it isn't one. After all, the testing happens regardless. Only the duration is uncertain. IPMA therefore defines an estimate as a planned activity with uncertainty regarding time or cost. You calculate that uncertainty using uncertainty analysis.

  2. An issue
    Is your specialist sick today? Then there is no longer any uncertainty about it. It is happening now, and then you have an issue. An issue is an event that has already occurred or that you can virtually no longer avoid. It requires immediate action. A risk lies in the future, giving you time to calmly choose how to respond.

In short, the question regarding a risk is: will it happen? With an estimate, it is: how much? And with an issue, what do we do now?

How do you determine how big a risk is?

For each risk, you look at two things: how likely is it and how significant is the impact? Probability relates to the cause, impact to the consequence. When considering impact, you think of lead time, costs, and quality, but also safety or the environment.

You assign a score to both. The book mentions a scale of 1 to 5. A finer scale seems more accurate, but provides a false sense of security. With a coarser scale, you cannot sufficiently distinguish risks from one another.

If you multiply the 2 scores, you get a number that you can use to compare risks. IPMA calls this the expected value. For example: the supplier delivers late. That is quite likely (4) and the impact is average (3). That gives 4 x 3 = 12. A data breach is less likely (2), but the impact is huge (5). That gives 2 x 5 = 10. This way you can see at a glance which risk deserves attention first.

Can you express the impact in euros? Then the calculation becomes even more concrete. Is there a 20% chance of a setback of €10.000? Then the expected damage is €2.000. The book calls that the expected monetary value.

Which 8 risk measures can you take?

Have you weighed your risks? Then, for each risk, you choose how to respond. IPMA lists eight measures. On paper, they look similar, yet they work very differently. Some address the cause, others the consequences. Still others shift part of the risk to someone else or prepare you for the worst. We will walk you through them one by one.

1. Avoid or prevent
You ensure that the probability or impact becomes zero, so that the risk simply disappears. Suppose your project relies on a new software tool that is not yet running anywhere. If you choose a proven tool, the risk of teething problems no longer exists. However, avoidance often comes at a price, such as less innovation.

2. Remove the source of risk
Here, you remove the cause yourself. A supplier who consistently delivers late is a clear source of risk. If you replace him with a reliable party, the source of the problem is gone.

3. Reduce the probability
Sometimes a risk simply persists. You can, however, make it less likely. Take the holiday example: you can train extra colleagues on the machines in advance. The shortage is still there in the summer, but the chance of errors is much smaller.

4. Reducing the impact
With this measure, you assume that the risk may occur. You simply ensure that the consequences are limited, to a level that is acceptable. What remains is what IPMA calls the residual risk. Do you incorporate extra quality checks during the holiday period? Then you spot errors immediately and do not have to reject an entire batch.

5. Sharing the risk
You share the risk with another party, who then bears part of the consequences if things go wrong. Think of an agreement in the contract with your supplier or insurance. Do be aware, however, that sharing can itself create a new risk. More on that later.

6. Accept
Sometimes doing nothing is the best choice. That sounds lazy, but it is a conscious decision. You accept risks that score low. This also applies if a measure costs more than it yields. Do record the risk in your risk register, however, so that everyone sees that you are keeping an eye on it.

7. Accept or increase to seize an opportunity
This one is special. You consciously take on more risk because there is an opportunity involved. The book mentions the chance to extend a season. That yields extra revenue, but your staff runs a higher risk of becoming overburdened. If, after careful consideration, you still choose that chance, you are increasing the risk with your eyes wide open.

8. Create an emergency plan
With this measure, you determine in advance what to do if the risk materializes. This also includes a risk budget. For major risks, such as resource scarcity or currency risks, the book refers to a disaster budget. A contingency plan must always be linked to this. Permission to use that budget is usually granted by the steering committee or the client.

How do you choose the right measure?

Usually, you place multiple options side by side. For each option, you ask two questions: what does this measure yield and what does it cost? IPMA calls this the cost-effectiveness of a measure. As a project manager, you present the options in a recommendation to the client. The client is ultimately responsible for risk management and makes the choice.

Are you finished after your measure?

Almost. After a measure, something often remains: the residual risk. That residual risk must fall within the risk appetite . This is the amount and type of risk your client is willing to accept to achieve the project goals. If the residual risk falls outside of this, your measure is not yet strong enough. Also, watch out for a sneaky side effect, because a measure can itself create a new risk. This is called a secondary risk.

The book provides an example. A construction entrepreneur takes out liability insurance. If the insurer excludes certain contractual provisions, the entrepreneur still has to bear part of the damage himself.

Who is responsible for a risk?

Every risk is assigned an owner. In simple projects, you, as the project manager, are usually that person. Does a risk directly affect the business case? Then it lies with the client. In complex projects, you often appoint separate risk owners.

Everything is recorded in the risk register. In it, you record the assessment, measures, and status for each risk. You update the register at least at every phase transition so that nothing slips through the cracks.

And what about chances?

Risk management is also about windfalls. An opportunity is something that could happen in the future and turn out well for your project. The book mentions low inflation, which could cause materials to become cheaper. You also record an opportunity using the same sentence. According to IPMA, every project manager therefore has a dual task: managing risks and seizing opportunities.

Are you going for IPMA C or B? Then you will also learn 4 measures to really seize an opportunity!

Get started yourself

Take your current risk list and select the 3 vaguest points. Rewrite them using the sentence: ' because..., the risk arises that..., with the result that... '. Then, choose 1 of the 8 measures for each risk. Chances are your list will look a lot less daunting afterwards.

Lagant Academy trains project managers for IPMA certification. In the IPMA D training, you prepare for risk management even before the first training day, using examples from your own work. View Lagant Academy's IPMA training courses and choose the level that suits you.

Frequently asked questions

What is the difference between a risk and an issue?
A risk may occur in the future. An issue is already present or can no longer be avoided and requires immediate action.

How many risk measures does IPMA have?
IPMA Compact lists 8 risk measures: avoidance, removal of the source, reduction of probability, reduction of impact, sharing, acceptance, acceptance or increase to seize an opportunity, and creating a disaster plan.

Is risk management part of the IPMA D exam?
Yes. The concepts, the 8 risk measures, and the risk register are part of the material for IPMA D, C, and B. The 4 opportunity measures are only part of C and B.

Sources

  • IPMA Compact BCD-PMO 2025 (v3.0), Lagant Management Consultants. Competency V11 Risks and opportunities: V11.1 Concepts, definitions and categories (p. 418 to 423), V11.2 Risk management framework and risk measures (p. 424 to 430), V11.3 Risk management techniques (p. 430 to 436).
  • IPMA Compact BCD-PMO 2025, section Reserves (pp. 352 to 353).
  • Lagant Academy, Daily Preparation IPMA D (2025).

V11 Risks and opportunities falls under the technical competencies (Practice) in IPMA Compact.